The Queensland Train Manufacturing Program (QTMP) will support South East Queensland's population and economic growth, as well as Cross River Rail and the Brisbane 2032 Olympic and Paralympic Games.
Downer and its sub-contractors are releasing detailed work packages for businesses to supply goods and services to the QTMP as they are required.
To register your interest in becoming a supplier, please create an account on the Supply TMR portal: https://supplytmr.benchon.com
Once registered, you will be notified about work packages relevant to your business as they are posted on the portal. You can also subscribe to receive QTMP email updates and be notified of upcoming supply chain events and information. Information about awarded packages will also be available.
Work packages upcoming on the Supply TMR portal include:
Schedule of supplier opportunities with DT Infrastructure for the Ormeau rail facility:
Trade package name |
Scheduled tender package issued |
Commencement date |
Concrete trades |
Oct-24 |
Apr-25 |
Formwork, reinforce and pour (RFP) |
Oct-24 |
Apr-25 |
Structural steel |
Oct-24 |
May-25 |
Cladding and roof work |
Oct-24 |
Jun-25 |
Blockwork/masonry |
Mar-25 |
Oct-25 |
Specialist jointing and grates |
Dec-24 |
Aug-25 |
Joinery and metalwork |
Mar-25 |
Aug-25 |
Services (in-ground) |
Oct-24 |
Apr-25 |
Services (reticulation) |
Oct-24 |
Jul-25 |
Handrails and balustrades |
Jan -25 |
Aug-25 |
Glazing |
Jan -25 |
Oct-25 |
Fencing and gates |
Apr-25 |
Oct-25 |
Finishes |
Apr-25 |
Oct-25 |
Subcontract of supply and installation of bridge walkways and handrails |
Nov-24 |
Nov-25 |
Supply of track materials/consumables (fasteners, plates and clips, insulators and pads) |
Mar-25 |
Sep-25 |
Subcontract of carpark and road works - asphalt |
Nov-24 |
Jan-25 |
Subcontract of road works – excluding asphalt |
Oct-24 |
Jan-25 |
Subcontract of supply and install of fencing, barriers and gates including QR fencing |
Apr-25 |
Jul-25 |
Subcontract of bridge works |
Mar-25 |
Jul-25 |
Subcontract of supply and install of CCTV UPS - CCTV cabinets, comms and data |
Apr-25 |
Dec-25 |
Supply of signalling relays |
Aug-25 |
May-26 |
Supply of signalling cables |
Aug-25 |
Mar-26 |
Supply of ETCS Balaises/equipment |
Sept-25 |
Mar-26 |
Supply of level crossing Equipment |
Oct-25 |
May-26 |
Supply of train gates |
Oct-25 |
May-26 |
Supply of racks - signalling |
Aug-25 |
Jan-26 |
Supply of FRP – Retaining structures, Reinforced Concrete Box Culverts, base slab |
Jan-25 |
Apr-25 |
Supply of transformers - signalling |
Aug-25 |
Mar-26 |
Subcontract of signalling installation |
Jul-25 |
Dec-25 |
Subcontract of flash butt welding yard works |
Nov-24 |
Feb-25 |
Subcontract installation of track and turnout |
May-25 |
Sept-25 |
Subcontract of supply and install of Electrical LV and associated infrastructure |
Oct-24 |
Aug-25 |
Subcontract of supply and install of buffer stop |
Sept-25 |
May-26 |
Subcontract of supply and install of Signs incl. Rail signage |
Jan-26 |
Jul-26 |
This table is current as of September 2024. |
Schedule of supplier opportunities with John Holland for the Torbanlea train manufacturing facility:
Trade Package Name |
Scheduled Tender Package Issued |
Forecast Commencement Period |
External work |
||
Supply capping material |
Aug-24 |
Dec-24 |
Supply structural fill material |
Aug-24 |
Dec-24 |
Supply ballast |
Aug-24 |
Jan-25 |
Security Fencing and Gates |
Aug-24 |
Feb-25 |
Metal enclosures |
Aug-24 |
Mar-25 |
Landscaping |
Aug-24 |
Jan-25 |
Finishes and Fitouts |
||
Warehouse shelving |
Sep-24 |
Mar-25 |
FFE |
Jul-24 |
Apr-25 |
Signage |
Aug-24 |
Jul-25 |
Joinery |
Oct-24 |
Jun-25 |
Tiling |
Nov-24 |
Jun-25 |
Blinds and curtain |
Nov-24 |
Jun-25 |
Carpet and Vinyl (incl Floor Prep) |
Aug-24 |
Jul-25 |
Toilet partitions |
Jul-24 |
Aug-25 |
Fixtures and Fittings |
Jul-24 |
Jul-25 |
Track and signalling |
||
Supply track materials ballast track |
Aug-24 |
Dec-24 |
Install ballast track |
JuAug-24 |
Mar-25 |
Safe working - rail corridor fencing / demarcation |
Aug-24 |
Feb-25 |
Safe working - track protection |
Aug-24 |
Feb-25 |
Install special works track equipment |
Aug-24 |
Jun-25 |
Install turnouts |
Aug-24 |
Apr-25 |
Track surfacing works |
Aug-24 |
Jul-25 |
Supply and install train gates |
Aug-24 |
Feb-25 |
Supply materials ballastless track – inc. Level crossing work |
Oct-24 |
Feb-25 |
Excavate, form, reo, pour overhead wiring footings |
Nov-24 |
Dec-24 |
Install and Erect Overhead Wiring Poles |
Aug-24 |
Jan-25 |
Supply and Install Overhead Wiring, Contact Wire and Fittings |
Aug-24 |
Jul-25 |
This table is current as of September 2024. |
Schedule of supplier opportunities with HRC for the Torbanlea train manufacturing facility:
Location |
Scheduled Tender Package Issued |
Forecast Award |
Facility maintenance |
Q3 2024 |
Q2 2025 |
Site consumables |
Q3 2024 |
Q4 2025 |
Equipment service |
Q3 2024 |
Q4 2025 |
Other services |
Q4 2024 |
Q2 2025 |
This table is current as of September 2024. |
Schedule of packages awarded:
Location |
Trade Package Name |
Supplier |
Ormeau rail facility |
Supply of RCBC Culverts |
Humes |
Ormeau rail facility |
Subcontract of Main Earthworks |
L&D Contracting |
Ormeau rail facility |
Temporary Bridge Design and Construct |
Brady Marine and Civil (BMC) |
Ormeau rail facility |
CCTV Camera's and Monitoring |
Blackbox |
Ormeau rail facility |
Site Facilities - Phase 1 |
Black Diamond |
Ormeau rail facility |
Early Works Civil Contract (TNAR) |
ALLROADS Pty Ltd |
Ormeau rail facility |
Subcontract of Ground improvement works - CMC and MSM |
Menard Pty Ltd |
Ormeau rail facility |
Temporary Works Design |
BG&E |
Ormeau rail facility |
Traffic Control - EW |
Schramm Group Pty Ltd |
Ormeau rail facility |
Rail Protection Officer and Recipient |
TPS |
Ormeau rail facility |
General Plant Hire Wet/Dry |
Egans Plant Hire Pty Ltd |
Ormeau rail facility |
Subcontract of precast unloading including RCBC, RCP and pits |
Uplift Cranes |
Ormeau rail facility |
Site Facilities - Phase 2 |
Black Diamond |
Ormeau rail facility |
Waste Removal Skips |
Cleanaway Operations |
Ormeau rail facility |
Goldmine Permanent Water Connection |
Landform Civil Pty Ltd |
Ormeau rail facility |
Water treatment plant (PFAS) |
Enviropacific |
Ormeau rail facility |
PFAS Consultancy Management |
BeneTerra |
Ormeau rail facility |
PFAS Project Engineer |
PD Project Delivery Pty Ltd |
Ormeau rail facility |
ECI - Buildings Work |
Hutchinsons Building |
Ormeau rail facility |
Signalling Consultant |
Light Rail Solutions |
Ormeau rail facility |
Supply of Geofabric |
Geofabrics Australasian Pty Ltd |
Ormeau rail facility |
VAC truck hire |
Dynamic Hydro Excavations |
Ormeau rail facility |
Labour hire |
United Personnel |
Ormeau rail facility |
Supply of interlocking equipment - signalling |
Hitachi STS Rail |
Ormeau rail facility |
Survey work |
WW Surveys |
Torbanlea train manufacturing facility |
Civil Works (Clear and Grub) |
Delta |
Torbanlea train manufacturing facility |
Structural Steel - Supply and Install |
Beenleigh Steel |
Torbanlea train manufacturing facility |
Wastewater Treatment Plant |
Axis Plumbing |
Torbanlea train manufacturing facility |
Reo Supply |
Neumann Steel |
Torbanlea train manufacturing facility |
Concrete Supply |
Boodles Concrete |
Torbanlea train manufacturing facility |
Reo Fix |
Top End Steel Structures |
Torbanlea train manufacturing facility |
Concrete Pump and Place |
Top End Steel Structures |
Torbanlea train manufacturing facility |
Gantry Cranes |
Modular Cranes |
Torbanlea train manufacturing facility |
Hydraulic Services |
Axis Plumbing |
Torbanlea train manufacturing facility |
Electrical, Comms and Security Services |
Klennar Murphy Electricalo |
Torbanlea train manufacturing facility |
NBN |
NBN |
Torbanlea train manufacturing facility |
Mechanical Services and BMS |
A.G. Coombs |
Torbanlea train manufacturing facility |
Fire Protection (Wet and Dry) |
Auscoast Fire |
Torbanlea train manufacturing facility |
Survey - Setout and As-Built Survey |
Surveyors at Work |
Rollingstock |
Traction systems |
ABB |
Rollingstock |
Passenger seats |
KFS |
Rollingstock |
HVAC |
Knorrs Bremse |
Rollingstock |
Signalling |
Hitachi |
Rollingstock |
Train mock-up construction |
Allweld |
This table is current as of September 2024. |